2020 Crackseal Program

The City of Inver Grove Heights will be conducting a crackseal project on several streets this summer as part of the City’s Pavement Management Program. This is considered a regular street maintenance item.

This project will involve routing of the cracks in the street and/or along the curb, filling the routed cracks with a bituminous sealant material, and then covering the sealant with a protectant to allow traffic.

Project timeline

The project is tentatively scheduled to start Monday, May 11, weather permitting, and the project will take approximately 1 to 2 weeks to complete.

Traffic Impacts

  • Please observe posted warning and no parking signs.
    • The Contractor has the option to post “No Parking” signs 24-hours in advance of any work and have any parked vehicle towed at the owner’s expense. Please abide by the signs if posted.
  • Access to private properties during cracksealing will be maintained to the fullest extent possible.
  • Please do not park on the streets from 7 a.m. to 7 p.m. during the project until the crackseal operation is completed and the street is swept in front of your property.